Next 'problem' - excavation -
Our land is filled up, pre-first have to 1.40m removed and then filled out again, this is still the population at the height of the neighbors to come.
This information can be found in our soil report that we had before the Planugsgespräch already filed with finger house.
Because of the slope of the plot we were under the preliminary features pointed to seek ever tender for the earthworks.
bit unfortunate was the attached wording that finger house we recommend a basement because of additional costs incurred by the slope and the resulting extra costs for retaining wall and support the base.
One wonders, then, already, what's up for Finger house. All documents were available, the architect was on site, the preliminary moves have been created and now recommends we were suddenly a cellar.
Our plan intends no basement.
re phone calls to our Customer Relations. It must be said at this point that they always tried to be weiterzuhelfen ... Now we are back thanks to her, a small step further .... Today, the site manager of the base plate to contact us and we'll add to next week, even with the civil contractors, site visit that site, after which finger house us an offer on the Excavation present. It is gratifying, at least, that our site managers very closely with the civil contractors in the neighboring village, which we favor also works.
We are curious what to expect, but give up hope that this problem is resolved.